How many days are required for Virtual Servers to Go-live?

Answer

Regarding arrowhead and ToSTNeT, once connectivity test has been confirmed and the preparations are complete, the checklist and application for go-live will be submitted. Using virtual servers in Production Environment will be possible from 4 business days after the application for production operation and approval of the checklist.