[Screen Help] Application for New JPX Co-Location Rack

[Screen Help] Application for New JPX Co-Location Rack
Category : 

Answer

 
1: Desired Start Date
Click Calendar button, and select the desired start date from the calendar.
You can also enter the date directly in yyyy/mm/dd format.
*Regarding delivery time for adding rack cabinet is 3 weeks, reserving a rack is 1week, and to reserve rack take 3 weeks.
 
2: Request Number of Racks
8kVA:  Enter the applying number of racks whose contract demand is up to 8kVA
4kVA:  Enter the applying number of racks whose contract demand is up to 4kVA
Bundle service (2kVA/10G):  Enter the applying number of services that include a rack whose contract demand is up to 2kVA, two 10G internal connection lines and two PTP lines.
Bundle service (2kVA/1G):  Enter the applying number of services that include a rack whose contract demand is up to 2kVA, two 1G internal connection lines and two PTP lines.
Reserve:  Enter the applying number of racks to reserve.
Reservation release:  Enter the applying number of racks to release the reservation.
*If you want to use the Bundle service, please contact JPX Service Desk (application procedure) before applying.